GSOE9820 Project Management WEEK8

1. Mid-term Exam

时长:1h15min
题数:15 questions(90% are multiple choice questions, including calculation)
内容:WEEK4, 6, 7, 8(Organizational Structure, Developing a project, Scheduling resources and costs, Reducing project duration, Progress and performance measurement and evaluation)
复习:Textbook Chapter 3, 6, 8, 9, 13 + Sandra's online videos

2. Reducing project duration

通常项目的constaint集中在三个方面:scope, time, cost。减少项目周期有许多优势,比如降低项目风险,获得提前完成合约的条约好处等。

思考减少项目周期的时候通常有两种情况:resourecs constrained, not constrainted。
(1)not constrained
通过增加投入、外包、早期规划、核心团队建设等方式来减少项目周期。
(2)constrained
通过对critical path的管理,减少项目scope,牺牲一部分产品质量的方式来实现。

项目周期的减少会直接降低indirect costs,增加direct costs。
Direct costs: Costs that are clearly chargeable to a specific work package. 例如材料费、设备费
Direct overhead costs: Costs incurred that are directly tied to an identifiable project deliverable or work package. 例如薪水、租金
Indirect overhead costs: Organisation costs indirectly linked to a specific package that are apportioned to the project. 例如监管费、咨询费
(overhead costs营运开支)

在减少项目周期的过程中,要不断确认critical path,往往项目周期的减少会使得critical path增加,项目的sensitivity增加。
常用术语:
normal time: is the low-cost, realistic, efficient method for completing an activity under normal conditions
crashing: Means shortening an activity
crash time: is the shortest possible time that an activity can realistically be completed in
crash cost: is the direct cost for completing an activity within the crash time
crash point: Represents the maximum time an activity can be compressed/reduced.

Cost-duration graph

通常减少项目周期的时候优先从critical activities,同时兼顾增长的费用最少。也就是说Shorten the critical activities with the smallest increase in cost per unit of time

Activity graph

对上图的activity graph而言,默认cost relationship是linear的,这个图的最大价值在于constant cost per unit of time,也就是图中斜线的slope。

如果cost是客户更加看重的部分,那么可以考虑减少project scope,让客户take more responsibility。

3. Progress and performance measurement and evaluation

对于PM(Project managers)来说,project evaluaiton and control是日常最重要的工作之一。
(1)Data collection
主要收集的数据是cost and schedule,以及潜在问题和对项目未来的预测。
(2)Project control
setting a baseline plan,常用方法是甘特图(Gantt charts),与WBS时不同的是,project control时所有的甘特图是用进度条来表示的。
-->
measuring progress and performance, 常用方法是project schedule control chart,以reporting period做横轴,time periods做纵轴,评估项目的进度是否符合计划,如下图。
-->
comparing plan against actual -->
taking action

Project schedule control chart

常用术语:
Earned Value(EV): Earned value is a project management technique for measuring project performance and progress. pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work. Earned value is the percent of original budget that has been earned by actual work completed.
Planned Value(PV)/ Budget Cost of Work Scheduled(BCWS): a valuation of planned work. The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline.
Actual Cost(AC): Actual cost of the work completed.
Cost Variance(CV): Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV - AC
Schedule Variance(SV): Schedule variance is the difference between the earned value and the baseline to date where SV = EV - PV

Project management process review:
WBS--OBS--Work packages (time, resources, budgets, responsibilities, performance standards)--Plan, shcedule baseline--Control(Time, cost, specifications by deliverables and organisation)

PV: Budgeted cost of the work scheduled
EV: Budgeted cost of the work completed
AC: Actual cost of the work completed

CV = EV - AC: Indicates if the work accomplished using labour and materials costs more or less than was planned at any point in the project
SV = EV - PV: Presents an overall assessment in dollar terms of the progress of all work packages in the project scheduled to date

Cost schedule graph

Performance indexes:
Cost performance index(CPI): Measures the cost efficiency of work accomplished to date. CPI = EV/AC
Scheduling performance index(SPI): Measures scheduling efficiency. SPI = EV/PV
Percent complete index: Indicates how much of the work accomplished is represented by the total budgeted (BAC) and actual (AC) dollars to date. PCIB = EV/BAC; PCIC = AC/EAC

index > 1.00: CPI under cost, SPI ahead of schedule;
index = 1.00: CPI on cost, SPI on schedule;
index < 1.00: CPI over cost, SPI behind schedule

Forecasint model:

Forecasting model
最后编辑于
©著作权归作者所有,转载或内容合作请联系作者
  • 序言:七十年代末,一起剥皮案震惊了整个滨河市,随后出现的几起案子,更是在滨河造成了极大的恐慌,老刑警刘岩,带你破解...
    沈念sama阅读 204,684评论 6 478
  • 序言:滨河连续发生了三起死亡事件,死亡现场离奇诡异,居然都是意外死亡,警方通过查阅死者的电脑和手机,发现死者居然都...
    沈念sama阅读 87,143评论 2 381
  • 文/潘晓璐 我一进店门,熙熙楼的掌柜王于贵愁眉苦脸地迎上来,“玉大人,你说我怎么就摊上这事。” “怎么了?”我有些...
    开封第一讲书人阅读 151,214评论 0 337
  • 文/不坏的土叔 我叫张陵,是天一观的道长。 经常有香客问我,道长,这世上最难降的妖魔是什么? 我笑而不...
    开封第一讲书人阅读 54,788评论 1 277
  • 正文 为了忘掉前任,我火速办了婚礼,结果婚礼上,老公的妹妹穿的比我还像新娘。我一直安慰自己,他们只是感情好,可当我...
    茶点故事阅读 63,796评论 5 368
  • 文/花漫 我一把揭开白布。 她就那样静静地躺着,像睡着了一般。 火红的嫁衣衬着肌肤如雪。 梳的纹丝不乱的头发上,一...
    开封第一讲书人阅读 48,665评论 1 281
  • 那天,我揣着相机与录音,去河边找鬼。 笑死,一个胖子当着我的面吹牛,可吹牛的内容都是我干的。 我是一名探鬼主播,决...
    沈念sama阅读 38,027评论 3 399
  • 文/苍兰香墨 我猛地睁开眼,长吁一口气:“原来是场噩梦啊……” “哼!你这毒妇竟也来了?” 一声冷哼从身侧响起,我...
    开封第一讲书人阅读 36,679评论 0 258
  • 序言:老挝万荣一对情侣失踪,失踪者是张志新(化名)和其女友刘颖,没想到半个月后,有当地人在树林里发现了一具尸体,经...
    沈念sama阅读 41,346评论 1 299
  • 正文 独居荒郊野岭守林人离奇死亡,尸身上长有42处带血的脓包…… 初始之章·张勋 以下内容为张勋视角 年9月15日...
    茶点故事阅读 35,664评论 2 321
  • 正文 我和宋清朗相恋三年,在试婚纱的时候发现自己被绿了。 大学时的朋友给我发了我未婚夫和他白月光在一起吃饭的照片。...
    茶点故事阅读 37,766评论 1 331
  • 序言:一个原本活蹦乱跳的男人离奇死亡,死状恐怖,灵堂内的尸体忽然破棺而出,到底是诈尸还是另有隐情,我是刑警宁泽,带...
    沈念sama阅读 33,412评论 4 321
  • 正文 年R本政府宣布,位于F岛的核电站,受9级特大地震影响,放射性物质发生泄漏。R本人自食恶果不足惜,却给世界环境...
    茶点故事阅读 39,015评论 3 307
  • 文/蒙蒙 一、第九天 我趴在偏房一处隐蔽的房顶上张望。 院中可真热闹,春花似锦、人声如沸。这庄子的主人今日做“春日...
    开封第一讲书人阅读 29,974评论 0 19
  • 文/苍兰香墨 我抬头看了看天上的太阳。三九已至,却和暖如春,着一层夹袄步出监牢的瞬间,已是汗流浃背。 一阵脚步声响...
    开封第一讲书人阅读 31,203评论 1 260
  • 我被黑心中介骗来泰国打工, 没想到刚下飞机就差点儿被人妖公主榨干…… 1. 我叫王不留,地道东北人。 一个月前我还...
    沈念sama阅读 45,073评论 2 350
  • 正文 我出身青楼,却偏偏与公主长得像,于是被迫代替她去往敌国和亲。 传闻我的和亲对象是个残疾皇子,可洞房花烛夜当晚...
    茶点故事阅读 42,501评论 2 343

推荐阅读更多精彩内容