2022-04-08(206)Engineering law and the ICE Contracts

16. “HEADINGS AND MARGINAL NOTES”. A drafting error in the previous edition is corrected.

17. CLAUSE REFERENCES. This definition permits the omission of the “hereof” which appears in the previous edition after each cross-reference to a clause number.

This tiny nod in the direction of modern and clear drafting appears to have exhausted the draftsman of this edition.

The definition applies only to clause references “herein”, i.e. in the conditions (general or special), not in the specification or other documents.

18. “ ‘COST’…DEEMED TO INCLUDE OVERHEAD COSTS WHETHER ON OR OFF… THE SITE”. Note that this definition only applies to references to cost in the conditions of contract (general or special), not in other contract documents.

Under cl. 13 (3) the contractor is entitled to cost incurred due to instructions and similarly restricted to cost in cls. 12 (3), 14 (6) and 31 (2). m′

Extra work or delay may cause real additional overhead costs to the contractor, for example where he has to engage extra supervisors on or off the site to deal with the additional work, or to employ for a longer period supervisors specially engaged for the particular works. Such cost is clearly recoverable under this definition. The contractor’s fixed overheads, for example rent of head office premises, are much more difficult.

In claiming for breach of contract where the contractor is not limited to recovering costs (p. 427), contractors traditionally include loss of overhead return. The example may be taken of a delay of six months for which the employer is responsible, in a contract that would have been performed in a year but for the delay. The contractor will show the annual amount towards payment of these fixed overheads that would have been earned by his resources engaged on the contract, and will seek to recover half that amount by way of damages on the grounds that had his resources been freed from the site and not retained there unproductively for a further six months they would have earned on another contract that further contribution to overheads (see further p. 370 on this formula). Such a claim is not for cost incurred because of the delay, in the sense that the contractor would have had to pay these overhead costs even if the delay had not happened, but is for loss of the opportunity to earn money out of which to pay those costs.

It might well be argued, therefore, that if a contractor is detained on the works unproductively for an extra six months because of an instruction of the engineer, the proportion of his head office costs equal to the proportion of his total turnover represented by the works does not constitute cost, in the sense of expenditure, incurred by reason of the instruction. That is, except in so far as he can show that during the period of the delay supervisors (with attendant office space, secretarial staff, etc.) in fact spent extra time dealing with the works by reason of the instruction.

It is possible that a wider interpretation will be adopted by the courts, in keeping with what seems to be the intention; that in so far as the contractor incurs extra costs on a site he is deemed to incur with them the appropriate proportion of the off-site expenses which, so to speak, “go with” the resources on site. A more forthcoming definition would have avoided this ambiguity. n

There will be other, unavoidable, anomalies in restricting the contractor to recovery of cost without loss of profits. For example, in an identical situation the costs recoverable by a contractor who hires plant will be greater than the costs recoverable by a contractor doing the work with his own plant (for which he will normally be entitled only to depreciation and other costs actually incurred while the plant is standing). A contractor doing the works on borrowed money will incur and presumably be entitled to recover interest charges; a contractor financing the works from his own resources may have no such head of recovery, since his equivalent loss will be the profit he would have made using elsewhere the money tied up in the works. Judicious arrangements when a job is undertaken, or even when some occurrence takes place for which the employer is bound to pay the contractor his cost, may increase the amount recoverable. n′

A distinction must be drawn between those clauses in these conditions which entitle the contractor only to cost incurred (e.g. cls. 13 (3) and 14 (6)), and the clauses which say that particular work shall be done “at the expense (cost) of the Employer” (cls. 20 (2), 36 (2)) or that “cost…shall be borne by the Employer” (cls. 17, 36 (3), 38 (2), 50). It is suggested that under both of the latter formulae the employer is bound to make reasonable payment to the contractor for the work, i.e. normally cost plus a reasonable percentage for profit. It might be argued that a subtle distinction is intended between the two formulae on the grounds that the definition of “cost” in this sub-clause means that under the last four clauses, overheads but not profit are payable; but there is no statement in any of those cases that it is the cost “incurred by the contractor” that is being referred to, and it is suggested that in context the word cost is used in the sense that the price for the operations is to be borne by the employer. For disruption claims see p. 370.

©著作权归作者所有,转载或内容合作请联系作者
  • 序言:七十年代末,一起剥皮案震惊了整个滨河市,随后出现的几起案子,更是在滨河造成了极大的恐慌,老刑警刘岩,带你破解...
    沈念sama阅读 199,830评论 5 468
  • 序言:滨河连续发生了三起死亡事件,死亡现场离奇诡异,居然都是意外死亡,警方通过查阅死者的电脑和手机,发现死者居然都...
    沈念sama阅读 83,992评论 2 376
  • 文/潘晓璐 我一进店门,熙熙楼的掌柜王于贵愁眉苦脸地迎上来,“玉大人,你说我怎么就摊上这事。” “怎么了?”我有些...
    开封第一讲书人阅读 146,875评论 0 331
  • 文/不坏的土叔 我叫张陵,是天一观的道长。 经常有香客问我,道长,这世上最难降的妖魔是什么? 我笑而不...
    开封第一讲书人阅读 53,837评论 1 271
  • 正文 为了忘掉前任,我火速办了婚礼,结果婚礼上,老公的妹妹穿的比我还像新娘。我一直安慰自己,他们只是感情好,可当我...
    茶点故事阅读 62,734评论 5 360
  • 文/花漫 我一把揭开白布。 她就那样静静地躺着,像睡着了一般。 火红的嫁衣衬着肌肤如雪。 梳的纹丝不乱的头发上,一...
    开封第一讲书人阅读 48,091评论 1 277
  • 那天,我揣着相机与录音,去河边找鬼。 笑死,一个胖子当着我的面吹牛,可吹牛的内容都是我干的。 我是一名探鬼主播,决...
    沈念sama阅读 37,550评论 3 390
  • 文/苍兰香墨 我猛地睁开眼,长吁一口气:“原来是场噩梦啊……” “哼!你这毒妇竟也来了?” 一声冷哼从身侧响起,我...
    开封第一讲书人阅读 36,217评论 0 254
  • 序言:老挝万荣一对情侣失踪,失踪者是张志新(化名)和其女友刘颖,没想到半个月后,有当地人在树林里发现了一具尸体,经...
    沈念sama阅读 40,368评论 1 294
  • 正文 独居荒郊野岭守林人离奇死亡,尸身上长有42处带血的脓包…… 初始之章·张勋 以下内容为张勋视角 年9月15日...
    茶点故事阅读 35,298评论 2 317
  • 正文 我和宋清朗相恋三年,在试婚纱的时候发现自己被绿了。 大学时的朋友给我发了我未婚夫和他白月光在一起吃饭的照片。...
    茶点故事阅读 37,350评论 1 329
  • 序言:一个原本活蹦乱跳的男人离奇死亡,死状恐怖,灵堂内的尸体忽然破棺而出,到底是诈尸还是另有隐情,我是刑警宁泽,带...
    沈念sama阅读 33,027评论 3 315
  • 正文 年R本政府宣布,位于F岛的核电站,受9级特大地震影响,放射性物质发生泄漏。R本人自食恶果不足惜,却给世界环境...
    茶点故事阅读 38,623评论 3 303
  • 文/蒙蒙 一、第九天 我趴在偏房一处隐蔽的房顶上张望。 院中可真热闹,春花似锦、人声如沸。这庄子的主人今日做“春日...
    开封第一讲书人阅读 29,706评论 0 19
  • 文/苍兰香墨 我抬头看了看天上的太阳。三九已至,却和暖如春,着一层夹袄步出监牢的瞬间,已是汗流浃背。 一阵脚步声响...
    开封第一讲书人阅读 30,940评论 1 255
  • 我被黑心中介骗来泰国打工, 没想到刚下飞机就差点儿被人妖公主榨干…… 1. 我叫王不留,地道东北人。 一个月前我还...
    沈念sama阅读 42,349评论 2 346
  • 正文 我出身青楼,却偏偏与公主长得像,于是被迫代替她去往敌国和亲。 传闻我的和亲对象是个残疾皇子,可洞房花烛夜当晚...
    茶点故事阅读 41,936评论 2 341

推荐阅读更多精彩内容